“Stakeholder management starts on day one”

30 June 2026
Marleen Dolman
Reading time: 5 minutes

Software projects often bring together globally operating teams, parallel workstreams and technical dependencies within a single development process. Dries Moors, software project leader at NXP, recognizes the importance of stakeholder management in aligning teams, priorities and interdependencies, and enrolled in a course at High Tech Institute.

In the high-tech industry, it’s no longer the case that a single software team works on a single product. Within edge AI projects, for example, specialists in security, machine learning, connectivity and signal processing collaborate on the same architecture. These are often separate teams, which, at larger companies such as NXP, also participate in multiple projects simultaneously from different locations worldwide. For project leaders like Dries Moors, this means constantly switching between different stakeholders.

Moors began his career as a software engineer at Philips and moved with the semiconductor division when it was spun off as NXP. As a software project leader, he’s now responsible for the timely delivery of the software components that go into a chip. NXP chips find their way into a wide range of applications. For example, the automotive industry is an important market: Virtually every newly produced car today contains multiple chips from the company. Closer to Moors’ own area of work, they’re also widely used in smart sensor solutions, insulin pumps and hearing aids.

Complexity

Especially in wearable products, chips need to be tiny and mustn’t draw too much power since batteries for these devices are often smaller than a fingernail. That’s already a challenge in itself, but current developments in machine learning (ML) and AI add yet another layer of complexity. “At the moment, the effort is to get this into a chip without requiring an entire external infrastructure,” Moors explains. “That demands very specific hardware with very specific software inside it. NXP is very good at that.”

However, because NXP also wants to serve the mass market, it’s important that the software can align with mainstream systems. This makes the projects in which Moors is involved highly complex. Within a single program, he works with teams covering security, signal processing, connectivity and model optimization, among other topics. “A large part of my time goes into aligning teams, resolving blockages and monitoring priorities and deadlines,” says Moors.

That’s precisely where the biggest challenges arise. Different stakeholders each have their own interests, priorities and expectations of a project. Some are mainly involved on the technical side, while others want to keep track of planning, risks or dependencies in relation to other projects. When information is shared too late, or when stakeholders are unexpectedly confronted with problems, this can have major consequences for the progress of a project. “A meeting can turn very quickly when people are caught off guard,” Moors explains. “That’s why stakeholder management is so important. You need to know who has influence, what information someone needs and when to share it.”

Prioritizing stakeholders

Within projects, choices constantly need to be made. As a result, schedules change, new dependencies emerge and priorities shift. When stakeholders are timely included in developments and on potential risks, teams can prepare for what’s coming and there’s more room to adjust before problems escalate. When certain parties aren’t involved early enough, or don’t get sufficient visibility into developments within a project, risks arise. To get a better grip on this, Moors took the “Project leadership” training at High Tech Institute.

The course placed a strong emphasis on stakeholder management. “I had expected it to be one of the topics,” Moors says. “But almost the entire training was about it. That turned out to be a good thing, because it allowed us to really go in depth.” According to Moors, the added value lay mainly in the practical implementation techniques. “How to map stakeholders, what information they need and how to structure that was all made very concrete.”

An important part of the training revolved around consciously selecting and prioritizing stakeholders. After all, they don’t all need to receive the same information or be involved equally. Moors: “You learn to look at who genuinely influences decisions, who mainly wants to be kept informed and which relationships you should actively invest in.”

You can also deliberately choose to engage certain people less actively. “Some stakeholders will come along regardless, while others structurally push back without actually having decision-making authority. Sometimes, you have to accept that you can’t put all your energy into that.”

To Moors, the training showed how to build in structure from the very start. The so-called project charter plays an important role here: documenting the boundaries, objectives and preconditions within which a project is executed. “That creates clarity about expectations,” he explains. “For yourself, but also for stakeholders.”

The course also strongly emphasized that stakeholder management shouldn’t begin when a project runs into problems, but that it must be part of the approach from day one. Stakeholders must be properly identified, kept on board in the right way and provide input in time. The training also helped structure this element “so that you don’t drown in the reporting lines you’re building up.”

Practical advice

Moors especially appreciated the focus on real-world practice. Trainer Wilhelm Claussen showed, among other things, how he himself has been structuring and following up on stakeholder information within projects for years. “I used to work mainly with loose notes. Following his example, I’ve been structuring much more deliberately. It makes things a lot less vague.”

The course also offered room for practical advice such as how to get started with stakeholder management, what tools are available and what to do once you have a document in place. There was plenty of space for participants to bring in their own real-world examples, and because the group was relatively small, it was possible to go deeper into specifics.

Although Moors says it’s still too early to draw firm conclusions about the effects on his ongoing projects, he does notice a shift in his perspective. “I’ve become more aware of the importance of stakeholder management from the very beginning of a project,” he says. “You only notice later on in a project how many problems you’ve prevented by having the right people on board from the start.”

This article was written in close collaboration with High Tech Institute.

Related content

“A requirement without constraints remains open to interpretation”

Dutch defense embraces Intelic’s software-first drone interoperability approach

Top jobs
Your vacancy here?
View the possibilities
in the media kit
Events
Courses
Headlines
  • ASIC design team spins out from Philips as ICwaves

    8 July 2026
  • Dutch defense embraces Intelic’s software-first drone interoperability approach

    8 July 2026
  • TNO and Destinus collaborate on radar seekers

    8 July 2026
  • Noviotech Campus sees another director go

    6 July 2026
  • UT appoints Gregor Halff as new executive board president

    6 July 2026
  • Reports: Semi equipment market to reach up to $250B in 2028

    1 July 2026
  • Japanese researcher proposes simpler high-NA EUV optics design

    25 June 2026
  • ASML partners with TNO on photonic chip pilot line

    24 June 2026
  • Dutch minister pushes back on US bid to tighten China chip controls

    24 June 2026
  • Alixlabs launches beta APS platform for non-litho patterning

    23 June 2026
  • Thales NL expands radar system production and test capacity

    23 June 2026
  • Robin Radar and TNO develop airborne radar

    22 June 2026
  • Nearfield closes record 330-million-euro funding round

    22 June 2026
  • Koen ten Hove appointed as CTO of Thales NL

    19 June 2026
  • Besi raises long-term targets on AI packaging and hybrid bonding demand

    18 June 2026
  • ABN Amro: AI and defense boom shakes up Dutch EMS sector

    17 June 2026
  • Nexperia stays profitable despite China disruption

    16 June 2026
  • ASML, TSMC and Imec scale 2D transistors to 50nm pitch on 300mm wafers

    15 June 2026
  • Optical interconnect market explodes to $39B by 2030

    15 June 2026
  • Forced layoffs avoided until May 2027 in union-backed ASML restructuring plan

    11 June 2026
Bits&Chips logo

Bits&Chips strengthens the high tech ecosystem in the Netherlands and Belgium and makes it healthier by supplying independent knowledge and information.

Bits&Chips focuses on news and trends in embedded systems, electronics, mechatronics and semiconductors. Our coverage revolves around the influence of technology.

Advertising
Subscribe
Events
Contact
Follow us on
High-Tech Systems Magazine (Dutch)
(c) Techwatch bv. All rights reserved. Techwatch reserves the rights to all information on this website (texts, images, videos, sounds), unless otherwise stated.
  • About
  • Memberships
  • Advertising
  • Videos
  • Contact
  • Search
Privacy settings

Bits&Chips uses technologies such as functional and analytical cookies to improve the user experience of the website. By consenting to the use of these technologies, we may capture (personal) data, unique identifiers, device and browser data, IP addresses, location data and browsing behavior. Want to know more about how we use your data? Please read our privacy statement.

 

Give permission or set your own preferences

Functional Always active
Functional cookies are necessary for the website to function properly. It is therefore not possible to reject or disable them.
Voorkeuren
De technische opslag of toegang is noodzakelijk voor het legitieme doel voorkeuren op te slaan die niet door de abonnee of gebruiker zijn aangevraagd.
Statistics
Analytical cookies are used to store statistical data. This data is stored and analyzed anonymously to map the use of the website. De technische opslag of toegang die uitsluitend wordt gebruikt voor anonieme statistische doeleinden. Zonder dagvaarding, vrijwillige naleving door je Internet Service Provider, of aanvullende gegevens van een derde partij, kan informatie die alleen voor dit doel wordt opgeslagen of opgehaald gewoonlijk niet worden gebruikt om je te identificeren.
Marketing
Technical storage or access is necessary to create user profiles for sending advertising or to track the user on a site or across sites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}

Your cart (items: 0)

Products in cart

Product Details Total
Subtotal €0.00
Taxes and discounts calculated at checkout.
View my cart
Go to checkout

Your cart is currently empty!

Start shopping

Notifications